railway TRACK MOTOR repair work station

scope: demolish, de-contaminate, drain sump construction, concrete replacement, anti slip floor all using silikal(r) mma resins

Project Date: 2018

Facility: Eastern Canada

sloped floor, drain sump, anti slip floor

for heavy motor repair

problem definition:

  • EXISTING EPOXY / URETHANE HAD FAILED IN ABOUT 2-3 MONTHS. BETTER, PROVEN OPTION NEEDED.

  • FAST RETURN-TO-SERVICE REQUIRED. CANNOT SHUTDOWN CRITICAL MAINTENANCE FACILITY FOR EXTENDED PERIOD OF TIME USING CEMENTITIOUS CONCRETE, ALLOW FOR 28 DAYS CURING, AND THEN INSTALL FINISHED FLOOR.

    • DEMOLITION OF ENTIRE SLAB, RE-SLOPING WITH NEW SLAB, NEW TRENCH DRAINAGE FACILITY: 5-6 WEEKS

    • REPAIR / RENOVATE WAS FASTER THAN REPLACE BETTER AT 11 DAYS.

  • WATER AND OIL NOT DRAINING ACCUMULATING IN THE WORK AREA.

  • SLIPPERY ENVIRONMENT

  • NO DRAIN SUMP LOCATED ON THE FLOOR. NEW SUMP AND DRAIN REQUIRED

  • NEED TO DEMO / ACCOMODATE PREVIOUS CRANE SUPPORT IN MIDDLE OF WORK AREA.

  • UNDERGROUND IN / OUT PIPING NEEDED TO BE INSTALLED

  • IMPROVE HOUSEKEEPING. EASIER TO CLEAN FLOOR NEEDED.